Define what must be delivered and when
Start with the proposed scope, due date and the qualified resources it needs. Estimate the work by resource and week; include preparation, review, rework and handover where relevant. An adviser reviewing the plan should be able to tell which estimates are measured, agreed or still assumptions. If effort is unknown, investigate it rather than enter zero. Capacity is a constraint on a price or sales plan, not evidence that customers will buy.
Count supply once and commitments once
For each person, machine or genuinely interchangeable pool, enter gross scheduled hours for a Monday-start week. Subtract unavailable or protected hours such as leave, administration or maintenance. This gives available hours. Record accepted jobs as workload, not also as unavailable time. Add the proposed package separately. Use the same hours basis throughout: do not compare person-days with machine-hours or count the same person again under another role. A pool is valid only if its members can actually perform that work.
Find the constraint, then compare a feasible response
Headroom = gross scheduled hours − unavailable/protected hours − accepted work − proposed work. A negative number is a shortage in that resource and week. Spare design hours do not replace an authorised review hour. Compare moving the due date, reducing scope, changing the sequence, or using a qualified resource with confirmed availability. Changing the proposed hours must change the scope or effort basis too; lowering an estimate merely to make a row green does not create capacity. Overtime, subcontracting and new hires require their own cost, quality and authority checks.
Check the real schedule before making the promise
Positive weekly headroom is necessary but not sufficient. The reviewer may only be available before the designer finishes; a machine may need a continuous block; two jobs may need the same resource on Tuesday. Check task dependencies and actual diary or equipment slots separately. Record the chosen response, any customer agreement, its owner and the review date. Recheck accepted work, absence and effort estimates when facts change. This template does not produce a staffing score, a universal utilisation target or an automatic accept/decline decision.