    Capacity Planning Template

    Work out whether the people or equipment needed for a commitment are actually available. Compare accepted and proposed work by resource and week, identify the constraint, and choose what must change before you promise delivery.

    Two sheets: Your capacity for your inputs and Example for the fictional studio. The workbook calculates available hours, total load and headroom, and flags missing or inconsistent inputs. No account or AI conversation required.

    The work brief keeps this resource reference. Add your completed file or notes there; downloaded worksheets are not read or imported automatically.

    Free to use and share · No account required · Updated 4 November 2026

    When it helps: An owner, team lead or adviser needs to assess a new commitment, find an overloaded resource, or revisit a delivery promise after availability changes. It also works for equipment measured in hours; it is not a shift roster or production-line scheduler.

    The working tool

    See it in use

    Paper Kite Design — a fictional two-person studio

    Can Mara and Luis deliver an additional design package by 13 November 2026 without displacing accepted work?

    Commitment and basis

    The studio wants to take on one additional package. It needs both design production and owner review; the roles are not interchangeable.

    A proposed package due 13 November

    The package requires 6 hours from Mara (2 for discovery and 4 for review) and 10 hours of Luis’s design work in the week starting 9 November 2026. Accepted client work must remain in place. These are invented teaching estimates, not observed productivity.

    Two resources, two separate constraints

    Mara is the only authorised reviewer in this example. Luis’s spare design time cannot substitute for Mara’s review. Hours reserved for administration, leave or other unavailability are deducted from scheduled time; accepted client jobs are recorded only as workload.

    Mara owns the delivery decision

    Before responding to the customer, Mara checks the project sequence, proposed deadline and both diaries. Any move to 20 November requires the customer’s agreement. The workbook is an aid to that decision, not approval.

    The question is not whether the studio has enough hours in total. It is whether each required resource has usable time in the right week and sequence.

    Do not promise 13 November. The owner-review resource is short by two hours even though the two people’s aggregate hours balance. A later date is a conditional option, not a commitment: check the sequence, customer agreement and the owner’s availability first.

    This is a fictional teaching example, not a client result.

    Define what must be delivered and when

    Start with the proposed scope, due date and the qualified resources it needs. Estimate the work by resource and week; include preparation, review, rework and handover where relevant. An adviser reviewing the plan should be able to tell which estimates are measured, agreed or still assumptions. If effort is unknown, investigate it rather than enter zero. Capacity is a constraint on a price or sales plan, not evidence that customers will buy.

    Count supply once and commitments once

    For each person, machine or genuinely interchangeable pool, enter gross scheduled hours for a Monday-start week. Subtract unavailable or protected hours such as leave, administration or maintenance. This gives available hours. Record accepted jobs as workload, not also as unavailable time. Add the proposed package separately. Use the same hours basis throughout: do not compare person-days with machine-hours or count the same person again under another role. A pool is valid only if its members can actually perform that work.

    Find the constraint, then compare a feasible response

    Headroom = gross scheduled hours − unavailable/protected hours − accepted work − proposed work. A negative number is a shortage in that resource and week. Spare design hours do not replace an authorised review hour. Compare moving the due date, reducing scope, changing the sequence, or using a qualified resource with confirmed availability. Changing the proposed hours must change the scope or effort basis too; lowering an estimate merely to make a row green does not create capacity. Overtime, subcontracting and new hires require their own cost, quality and authority checks.

    Check the real schedule before making the promise

    Positive weekly headroom is necessary but not sufficient. The reviewer may only be available before the designer finishes; a machine may need a continuous block; two jobs may need the same resource on Tuesday. Check task dependencies and actual diary or equipment slots separately. Record the chosen response, any customer agreement, its owner and the review date. Recheck accepted work, absence and effort estimates when facts change. This template does not produce a staffing score, a universal utilisation target or an automatic accept/decline decision.

    Take the work further if useful

    Use the tool yourself, prepare business-specific work, or involve an expert for feedback, revision, implementation or ongoing support. Choose what the situation needs.

    Capacity and resource-constrained scheduling are established management practices. This workbook, practical explanation and fictional design-studio example are original Navigate material. No client result or universal utilisation benchmark is implied.