    RACI Matrix Template

    Agree who does the work, who owns the result and what they can decide. Start with the editable matrix for a shared project, or use the short delegation agreement on its own for one person’s work.

    The work brief keeps this resource reference. Add your completed file or notes there; downloaded worksheets are not read or imported automatically.

    Free to use and share · No account required · Updated 4 November 2026

    When it helps: A project involves several people, handovers are unclear, or delegated work keeps returning to the owner for routine decisions.

    The working tool

    See it in use

    Fictional community workshop project

    Who owns the workshop work, and which decisions can the coordinator make without asking the sponsor again?

    RACI matrix

    A small training business is running one customer workshop. The sponsor agrees the purpose and budget; the coordinator organises delivery. The facilitator and venue lead own distinct parts of the work.

    On a narrow screen, scroll the table sideways or focus it and use the arrow keys.

    Activity or decisionSponsorCoordinatorFacilitatorVenue lead
    Agree the workshop outcome and budgetA/RCCI
    Arrange the room and materials within the agreed budgetIA/RCC
    Prepare and deliver the sessionICA/RI
    Confirm room readiness and accessICCA/R
    Decide a change to scope or total budgetARCC
    Collect feedback and record the follow-up actionsIA/RCI

    The coordinator handles routine arrangements. A budget increase returns to the sponsor with an option and its consequences; it does not stall every other task.

    The letters show coordination; the delegation discussion makes the authority, support and expected result real. Check both with the people doing the work.

    R = Responsible · A = Accountable · C = Consulted · I = Informed. One A and at least one R per activity; A/R can be the same person. This is a fictional teaching example, not a client result.

    Fill the matrix around actual work

    Name one project or process, the people involved and observable activities or decisions. Responsible does the work; Accountable owns the result or decision; Consulted gives input before it is settled; Informed receives the outcome. Give each row exactly one A and at least one R. A/R may be the same person. Leave a cell empty where no involvement is needed; do not consult everyone on everything.

    Agree authority as well as responsibility

    Use the second page to agree the result, completion standard, responsibilities, decision authority, limits, support and check-in. It works for a colleague, consultant, contractor or fractional specialist; it is not an employment contract or legal appointment. A letter in a matrix does not grant spending, professional or other authority. For work owned by one person, the short agreement may be enough without a RACI grid.

    Walk through routine work and an exception

    Ask each person what they do next, what they can decide and when they need help. Try one ordinary handover and one change outside the agreed limit. Correct gaps in authority, time or information before relying on the arrangement. Revisit it when the people, work or constraints change; use an SOP for the detailed recurring steps.

    Take the work further if useful

    Use the tool yourself, prepare business-specific work, or involve an expert for feedback, revision, implementation or ongoing support. Choose what the situation needs.

    RACI is an established responsibility-assignment method. The explanation, working matrix, delegation prompts and fictional example are original Navigate material.